Apologies for Absence
Minutes:
Apologies for absence were received from Councillor J L King and
Mr Ian Haldenby who both observed the meeting remotely via
Microsoft Teams.
|
2. |
Declarations of Members' Interests
Minutes:
In
relation to Minute Five on the agenda, Councillor P A Skinner
declared he was a member of South East Councils
Partnership.
In
relation to Minute Four on the agenda, Councillor P E Coupland
declared he was a member of Lincolnshire Pension Fund Pension
Committee.
|
3. |
Minutes of the meeting held on 28 March, 2022 PDF 417 KB
Minutes:
RESOLVED
That
the minutes of the meeting held on 28 March 2022 be confirmed and
signed by the Chairman as a correct record.
|
4. |
International Audit Standard - Response to Management Processes Questions PDF 472 KB
(To
receive a report by Lucy Pledge, Head of Internal Audit and Risk
Management, which provides the Committee with an assessment around
whether the Council and Pension Fund financial statements may be
mis-stated due to fraud or error)
Additional documents:
Minutes:
Consideration was given to a report produced by the Head of
Internal Audit and Risk Management which provided the Committee
with an assessment around whether the Council and Pension Fund
financial statements may be mis-stated due to fraud or
error.
Responses were made to
questions from members of the Committee on the following
topics:
- Valuation of Highways Assets – Work was ongoing to
establish appropriate estimations for Council assets, particularly
those of highways infrastructure, which may go on to impact to time
scales for accounts sign off. The assets within the Highways
network were discrete, thus, future improvements to a local section
impacted upon the wider network. However, there was a concern that,
as assets were being repaired, the maintained sections were not
removed from the accounts. This raised a query from the external
auditors that the gross cost may have been overstated within the
accounts. While depreciation occurred among highways assets,
officers were confident that the network value of the road network
was appropriate. CIFA, working with external auditors, issued a
short-term consultation as a solution to this financial
year’s accounts which was due to conclude
imminently.
- Anticipated Future Challenges – The Council benefitted
from a strong internal control framework which continuously adapted
to developing challenges. Moreover, all relevant professional
networks were engaged with to promote sharing best practice and
undertaking of horizon scanning. The Counter Fraud Plan included
national framework benchmarking and exercised a proactive Counter
Fraud Strategy.
- The
Council’s Property Portfolio – Properties were revalued
on a five-year rolling programme by the Council’s external
contractor. Upon revaluation, if material changes were identified,
the Council could request a revaluation of all properties.
Moreover, the five-year programme was recommended within the CIFA
accounting code of practice. A valuation, arising at the close the
previous financial year, resulted in an increase to a new asset,
the Energy from Waste Plant. Upon this valuation, officers
requested that it be revalued.
- Geopolitical Events Impacting on Lincolnshire Pension Fund
Valuations – A response would be circulated in writing to the
Audit Committee prior to the next meeting.
RESOLVED
That the
Audit Committee endorse the assessment, agreeing that it accurately
reflected the Council’s management process to minimise the
risk of fraud or error in the County Council and Pension Fund
financial statements.
|
5. |
Internal Audit - External Quality Assessment 2022 PDF 405 KB
(To
receive a report by Lucy Pledge, Head of Internal Audit and Risk
Management, which provides the Committee with information on the
result of the external quality assessment undertaken on Assurance
Lincolnshire in March 2022)
Additional documents:
Minutes:
Consideration was given to a report produced by the Head of
Internal Audit and Risk Management which provided the Committee
with information on the result of the external quality assessment
undertaken on Assurance Lincolnshire in March 2022.
Members stressed their
appreciation of the Council’s full conformity to the External
Quality Assessment 2022.
Responses were made to
questions from members of the Committee on the following
topics:
RESOLVED
- Remote Working – Internal Audit operated in a hybrid
manner for a long time, thus complete remote working’s during
the Covid-19 Pandemic, while challenging, was supported by
established precedent and effective technology. Face-to-face
engagements and working practices still held a necessary function
within the team. New starters in the Audit Teams were invited to
spend time in the office five days a week during the beginning of
their employment to fully apprise them within internal
practices.
- Staffing – The market for professional staff continued to
be competitive, particularly as locational demands ceased through
remote working arrangements. The Council recently benefitted from
several successful recruitment exercises through internal
development schemes and external advertisements with broader
candidate specifications. It was, however, acknowledged that
broader candidate specification resulted in an extended time for
effective autonomous development. Apprenticeships were promoted for
internal staff seeking to progress through levels six and seven, in
addition to entry level three auditors. Members were assured that
extensive recruitment enabled effective succession planning for
more senior roles.
- Resourcing
Demands – The Audit Team operated a business plan stating key
strategy, including income generation targets, however prioritised
support for internal clients and partners within Lincolnshire.
Currently, the Audit Team sought to maintain its current clientele
rather than expand operations.
- Assurance Lincolnshire
– Assurance
Lincolnshire sought to protect the quality of the internal
audit function within Lincolnshire. Where Local Councils operated
their internal audit function internally, Lincolnshire County
Council (LCC) worked collaboratory to share best practice.
Currently, LCC was in partnership with East Lindsey and the City of
Lincoln District Councils, in addition Nottinghamshire County
Council was an affiliate member of Assurance Lincolnshire.
Moreover, LCC benefitted from an informal working relationship with
North Lincolnshire Council (NLC) and North East Lincolnshire
Council (NELC) for audit matters of joint public
health.
- Data Analytics – The Council already operated data
analytics across its financial systems but hoped to expand this
onto its wider transactional systems. In addition, officers were
hoping to create a dedicated IT resource while maintaining an
expected standard of IT literacy throughout the Audit Team. Bids
were being planned for development for workforce
development.
RESOLVED
The Audit
Committee noted the positive outcome of the External Quality
Assessment for Assurance Lincolnshire and were assured over the
quality and effectiveness of the Council's Internal Audit
Function.
|
6. |
Corporate and Statutory Annual Complaints Report 2021/22 PDF 377 KB
(To receive a report
by Shagofta Noreen, Complaints Manager - Business Support, which
provides an analysis of corporate and statutory complaints received
by Lincolnshire County Council during the year
2021/2022)
Additional documents:
Minutes:
Consideration was given to a report produced by the Complaints
Manager - Business Support which provided the Committee with
analysis of corporate and statutory complaints received by
Lincolnshire County Council during the year 2021/2022.
Members of the
Committee felt that they would appreciate an update report six
months after the annual report.
Responses were made to
questions from members of the Committee on the following
topics:
- Complaint Actions – Quarterly reports were produced for
directorates enabling them to create actions plans to reduce
customer dissatisfaction particularly exploring opportunities for
staff training. The increase in overall contacts, officers felt,
was indicative of an accessible and robust complaints
process.
- Highways Complaints
– A significant project was ongoing to improve services
through keeping customers up to date of defect status and planned
future developments through Fix My Street. An increasing number of
complaints were being resolved in favour of the complainant
resulting in early resolution of customer
dissatisfaction.
- Presentational concerns – Officers acknowledged
Members’ presentational concerns in relation to the omission
of 2020/21 total contacts from the ‘Comparison of Contacts
and Complaints’ chart. It was clarified that, in relation to
the Reasons for ‘Complaint where Fault was Found’
chart, Lack of Service and Lack of Communication, listed within the
key, represented a nominal figure. Officers however appreciated
that, in future, inclusion of comparative data for the former chart
and a numerical breakdown of the latter chart would be beneficial
to Members.
- Seriousness of Complaints – The reasons for, and action
arising from, complaints, remained consistent with previous years.
In instances of acutely serious complaints immediate prioritisation
was initiated to ensure the appropriate steps were
taken.
- Misdirected Complaints – The complaints process contained
a facility for redirecting complaints to different council’s
or bodies. Moreover, where a complaint was received from another
council or body, these were logged with the respective area and in
the body they came from.
- Adult Social Care – Complaints of timescale deficiencies
were mitigated through appropriate expectations being set and
effective communicating, this had been fed back to all service
areas. There was no significant increase in upheld complaints that
were escalated to the Parliamentary Health Services Ombudsman or
the Local Government Social Care Ombudsman and, generally, their
investigation conclusion reflected that of the Council.
- Household Waste Recycling Centres – Complaints relating to
restrictions on material relate, mainly, to the first quarter due
to limited booking arrangements still being in place. These
complaints had been relayed to relevant service areas.
- Heads of Service Actions – In addition to reporting to
Directorate Leadership Teams, complaints formed part of the
Corporate Dashboard and fed through to Corporate Leadership Team
and subsequently Directorate Leadership Teams. Officers were
confident that they had a robust system which promoted effective
action against complaints.
RESOLVED
1.
That the findings of the Corporate and Statutory
Annual Complaints Report 2021/22 be acknowledged to enable them to
be published externally.
2.
That the Audit Committee receive an update following
six months of this meeting.
|
7. |
Information Assurance Annual Report 2021/22 PDF 389 KB
(To
receive a report by David Ingham, Head of Information Assurance,
which summarises key activity undertaken by the Information
Assurance (IA) team during 2021/22)
Additional documents:
Minutes:
Consideration was given to a report produced by the Head of
Information Assurance which summarised key activity undertaken by
the Information Assurance (IA) team during 2021/22.
Responses were made to
questions from members of the Committee on the following
topics:
- Data Breach Complaints – If a member of the public issued
a complaint through the Information Commissioner's Office (ICO),
the Council may not be made aware until a number of months passed
since the first contact, thus, there may be a backlog still to be
revealed. However, officers were confident that the number of
complaints remained lower than last year.
- Core information assurance E-Learning – While only 82 per
cent of staff had completed the E-Learning training per annum, the
figure was taken from all employees of the Council. Some of whom
joined, or departed, from the organisation within that annual
period. Officers were working with HR to develop a greater
breakdown of information. Moreover, staff were encouraged to
undertake training throughout the year with strong support from
senior management. The ICO were satisfied from all staff to be
trained over a two-year period.
- Accessible Language – Officers, appreciating their
technical language may not be accessible to the wider staffing of
the Council, undertook an exercise with a test group to communicate
their message in plain English.
RESOLVED
1.
That the information assurance activity for 2021/22
be noted.
2.
That the key activity demonstrating that the IA
function remains effective and is relevant to the council's needs
be noted.
|
8. |
Work Programme PDF 463 KB
(To
receive a report by Lucy Pledge, Head of Internal Audit and Risk
Management, which invites the Committee to consider its work
programme for the upcoming year)
Minutes:
The
Head of Internal Audit and Risk Management introduced the Work
Programme which provided the Committee with core assurance
activities currently scheduled for the 2021 work
programme.
The
Committee requested that the Complaints’ report come back to
the committee after six months of this meeting.
Members asked when the Integration of Health and Social Care
system would be brought to the Committee while acknowledging that
the system, to be implemented in July, would need time to embed as
to effectively analysis assurance.
RESOLVED
That the work programme as amended above be approved.
|