6 Delivery of HR Administration, Payroll, Exchequer, Adult Care Finance and the Customer Service Centre (CSC) pdf icon PDF 1004 KB

(To receive a report by the Executive Director – Resources which seeks approval for a mix of new commissioning arrangements as part of the future model of delivery of Corporate Support Services including HR Administration, Payroll, Exchequer, Adult Care Finance and the Customer Service Centre)

Additional documents:

Decision:

1.    That the future services design and sourcing approach be approved as follows:

a)    The entering into of a shared service arrangement with Hoople Limited for the delivery of HR Administration and Payroll to the Council and to schools;

 

b)    The outsourcing of the operation of the Customer Service Centre services to external suppliers;

 

c)    That the Council retains responsibility for digital transformation and the technology that supports it using a mixed model for resourcing transformation with a combination of in-house resource and external expertise secured as and when required;

 

d)    The insourcing of the Adult Social Care and Exchequer services.

 

2.    That the carrying out of the necessary procurement processes to secure the services of external suppliers referred to in 1b and 1c above, be approved.

 

3.    That authority be delegated to the Executive Director – Resources, in consultation with the Leader of the Council, and for 1b and 1c above with the Executive Councillor for Children’s Services, Community Safety and Procurement, and for 1b above with the Executive Councillor for People Management and Corporate Property, to take all necessary decisions and steps to progress the new commissioning arrangements referred to in paragraph 1 above and to progress the procurements referred to in paragraph 2 above, up to and including the award of contracts.

Minutes:

The Executive received a report which outlined options for the delivery of support services following the expiration of the Corporate Support Services Contract with Serco at the end of March 2024, and which could not be extended.  This contract included the provision of IMT Services (previously dealt with by Executive on 4 May 2022), Finance Services, HR Administration and Payroll and the Customer Service Centre.  Approval was sought for the mix of new commissioning arrangements as part of the future model of delivery and authority to commence procurement for the proposed outsourced service.

 

It was highlighted that the model of multi-stream contracts being let to prime providers so that a single outsourcing company (e.g. Serco) was responsible for a wide range of services had fallen out of favour with both providers and local authorities, due to a reduction in possible savings as the public sector has become more efficient.  As such, a mix of outsourcing and in-sourcing of services had been proposed.

 

The Overview and Scrutiny Management Board considered this report at its meeting held on 26 May 2022.

 

HR Administration and Payroll

 

The proposed approach was to enter into a shared service arrangement with Hoople Limited.  The Council was one of three shareholders of Hoople which was a Teckal company employing around 500 staff.  The Council’s payroll was complex and Hoople were experienced in delivering Council, schools and NHS payroll, although not Fire and Rescue. 

 

The Chairman of the Overview and Scrutiny Management Board presented the comments of the Board and it was reported that the Board accepted the arrangement that insourcing of this service would be too challenging and noted that Hoople did have experienced staff and therefore supported this aspect of the model.

 

During discussion by the Executive, the following was highlighted:

 

·       This report was welcomed.  However, it was commented that particular regard should be given to the complexities generated by the Fire and Rescue payroll.  It was highlighted that it was understood that Hoople would be looking to national providers to assist with this aspect of payroll.  The Executive was also advised that the payroll testing for Fire and Rescue was currently going well.

·       Concerns were raised regarding the increase in the level of payroll work and assurance was sought that Hoople would be able to manage the increasing workload.  Officers advised that they were confident that this would be managed, and the due diligence that was carried out successfully in 2018 would be updated and repeated following the decision of the Executive, to provide the necessary assurance to proceed.

·       It was important to note that any staff that TUPE’d across to Hoople would be able to continue to work in Lincoln.  It was confirmed that engagement with Serco staff, Hoople and HR officers would be taking place in the coming weeks.

 

Customer Service Centre (CSC) and Digital Transformation

 

The preferred option was to outsource the CSC as a single operational service, with the key technology selected and owned by the Council and where the responsibility  ...  view the full minutes text for item 6


 

 
 